10 Performance and Breach 10 Performance and Breach

Week 10

10.1 Morin Building Products Co. v. Baystone Construction, Inc. 10.1 Morin Building Products Co. v. Baystone Construction, Inc.

MORIN BUILDING PRODUCTS COMPANY, INC., Plaintiff-Appellee, v. BAYSTONE CONSTRUCTION, INC., Defendant-Appellant.

No. 82-2451.

United States Court of Appeals, Seventh Circuit.

Argued May 12, 1983.

Decided Sept. 16, 1983.

Alan H. Lobley, Ice, Miller, Donadio & Ryan, Indianapolis, Ind., for defendant-appellant.

Craig Pinkus, Mitchell, Hurst, Pinkus, Jacobs & Dick, Indianapolis, Ind., for plaintiff-appellee.

Before POSNER and COFFEY, Circuit Judges, and FAIRCHILD, Senior Circuit Judge.

POSNER, Circuit Judge.

This appeal from a judgment for the plaintiff in a diversity suit requires us to interpret Indiana’s common law of contracts. General Motors, which is not a party to this case, hired Baystone Construction, Inc., the defendant, to build an addition to a Chevrolet plant in Muncie, Indiana. Bay-stone hired Morin Building Products Company, the plaintiff, to supply and erect the aluminum walls for the addition. The contract required that the exterior siding of the walls be of “aluminum type 3003, not less than 18 B & S gauge, with a mill finish and stucco embossed surface texture to match finish and texture of existing metal siding.” The contract also provided “that all work shall be done subject to the final approval of the Architect or Owner’s [General Motors’] authorized agent, and his decision in matters relating to artistic effect shall be final, if within the terms of the Contract Documents”; and that “should any dispute arise as to the quality or fitness of materials or workmanship, the decision as to acceptability shall rest strictly with the Owner, based on the requirement that all work done or materials furnished shall be first class in every respect. What is usual or customary in erecting other buildings shall in no wise enter into any consideration or decision.”

Morin put up the walls. But viewed in bright sunlight from an acute angle the exterior siding did not give the impression of having a uniform finish, and General Motors’ representative rejected it. Bay-stone removed Morin’s siding and hired another subcontractor to replace it. General Motors approved the replacement siding. Baystone refused to pay Morin the balance of the contract price ($23,000) and Morin brought this suit for the balance, and won.

The only issue on appeal is the correctness of a jury instruction which, after quoting the contractual provisions requiring that the owner (General Motors) be satisfied with the contractor’s (Morin’s) work, states: “Notwithstanding the apparent finality of the foregoing language, however, the general rule applying to satisfaction in the case of contracts for the construction of commercial buildings is that the satisfaction clause must be determined by objective criteria. Under this standard, the question is not whether the owner was satisfied in fact, but whether the owner, as a reasonable person, should have been satisfied with the materials and workmanship in question.” There was much evidence that General Motors’ rejection of Morin’s exterior siding had been totally unreasonable. Not only was the lack of absolute uniformity in the finish of the walls a seemingly trivial defect given the strictly utilitarian purpose of the building that they enclosed, but it may have been inevitable; “mill finish sheet” is defined in the trade as “sheet having a nonuniform finish which may vary from sheet to sheet and within a sheet, and may not be entirely free from stains or oil.” If the instruction was correct, so was the judgment. But if the instruction was incorrect — if the proper standard is not whether a reasonable man would have been satisfied with Morin’s exterior siding but whether General Motors’ authorized representative in fact was — then there must be a new trial to determine whether he really was dissatisfied, or whether he was not and the rejection therefore was in bad faith.

Some cases hold that if the contract provides that the seller’s performance must be to the buyer’s satisfaction, his rejection— however unreasonable — of the seller’s performance is not a breach of the contract unless the rejection is in bad faith. See, e.g., Stone Mountain Properties, Ltd. v. Helmer, 139 Ga.App. 865, 869, 229 S.E.2d 779, 783 (1976). But most cases conform to the position stated in section 228 of the Restatement (Second) of Contracts (1979): if “it is practicable to determine whether a reasonable person in the position of the obligor would be satisfied, an interpretation is preferred under which the condition [that the obligor be satisfied with the obligee’s performance] occurs if such a reasonable person in the position of the obligor would be satisfied.” See Farnsworth, Contracts 556-59 (1982); Annot., 44 A.L.R.2d 1114, 1117, 1119-20 (1955). Indiana Tri-City Plaza Bowl, Inc. v. Estate of Glueck, 422 N.E.2d 670, 675 (Ind.App.1981), consistently with hints in earlier Indiana cases, see Andis v. Personett, 108 Ind. 202, 206, 9 N.E. 101, 103 (1886); Semon, Bache & Co. v. Coppes, Zook & Mutschler Co., 35 Ind.App. 351, 355, 74 N.E. 41, 43 (1905), adopts the majority position as the law of Indiana.

We do not understand the majority position to be paternalistic; and paternalism would be out of place in a case such as this, where the subcontractor is a substantial multistate enterprise. The requirement of reasonableness is read into a contract not to protect the weaker party but to approximate what the parties would have expressly provided with respect to a contingency that they did not foresee, if they had foreseen it. Therefore the requirement is not read into every contract, because it is not always a reliable guide to the parties’ intentions. In particular, the presumption that the performing party would not have wanted to put himself at the mercy of the paying party’s whim is overcome when the nature of the performance contracted for is such that there are no objective standards to guide the court. It cannot be assumed in such a case that the parties would have wanted a court to second-guess the buyer’s rejection. So “the reasonable person standard is employed when the contract involves commercial quality, operative fitness, or mechanical utility which other knowledgeable persons can judge .... The standard of good faith is employed when the contract involves personal aesthetics or fancy.” Indiana Tri-City Plaza Bowl, Inc. v. Estate of Glueck, supra, 422 N.E.2d at 675; see also Action Engineering v. Martin Marietta Aluminum, 670 F.2d 456, 460-61 (3d Cir.1982).

We have to decide which category the contract between Baystone and Morin belongs in. The particular in which Morin’s aluminum siding was found wanting was its •appearance, which may seem quintessentially a matter of “personal aesthetics,” or as the contract put it, “artistic effect.” But it is easy to imagine situations where this would not be so. Suppose the manager of a steel plant rejected a shipment of pig iron because he did not think the pigs had a pretty shape. The reasonable-man standard would be applied even if the contract had an “acceptability shall rest strictly with the Owner” clause, for it would be fantastic to think that the iron supplier would have subjected his contract rights to the whimsy of the buyer’s agent. At the other extreme would be a contract to paint a portrait, the buyer having reserved the right to reject the portrait if it did not satisfy him. Such a buyer wants a portrait that will please him rather than a jury, even a jury of connoisseurs, so the only question would be his good faith in rejecting the portrait. Gibson v. Cranage, 39 Mich. 49 (1878).

This case is closer to the first example than to the second. The building for which the aluminum siding was intended was a factory — not usually intended to be a thing of beauty. That aesthetic considerations were decidedly secondary to considerations of function and cost is suggested by the fact that the contract specified mill-finish aluminum, which is unpainted. There is much debate in the record over whether it is even possible to ensure a uniform finish within and among sheets, but it is at least clear that mill finish usually is not uniform. If General Motors and Baystone had wanted a uniform finish they would in all likelihood have ordered a painted siding. Whether Morin’s siding achieved a reasonable uniformity amounting to satisfactory commercial quality was susceptible of objective judgment; in the language of the Restatement, a reasonableness standard was “practicable.”

But this means only that a requirement of reasonableness would be read into this contract if it contained a standard owner’s satisfaction clause, which it did not; and since the ultimate touchstone of decision must be the intent of the parties to the contract we must consider the actual language they used. The contract refers explicitly to “artistic effect,” a choice of words that may seem deliberately designed to put the contract in the “personal aesthetics” category whatever an outside observer might think. But the reference appears as number 17 in a list of conditions in a general purpose form contract. And the words “artistic effect" are immediately followed by the qualifying phrase, “if within the terms of the Contract Documents,” which suggests that the “artistic effect” clause is limited to contracts in which artistic effect is one of the things the buyer is aiming for; it is not clear that he was here. The other clause on which Baystone relies, relating to the quality or fitness of workmanship and materials, may seem all-encompassing, but it is qualified by the phrase, “based on the requirement that all work done or materials furnished shall be first class in every respect” — and it is not clear that Morin’s were not. This clause also was not drafted for this contract; it was incorporated by reference to another form contract (the Chevrolet Division’s “Contract General Conditions”), of which it is paragraph 35. We do not disparage form contracts, without which the commercial life of the nation would grind to a halt. But we are left with more than a suspicion that the artistic-effect and quality-fitness clauses in the form contract used here were not intended to cover the aesthetics of a mill-finish aluminum factory wall.

If we are right, Morin might prevail even under the minority position, which makes good faith the only standard but presupposes that the contract conditioned acceptance of performance on the buyer’s satisfaction in the particular respect in which he was dissatisfied. Maybe this contract was not intended to allow General Motors to reject the aluminum siding on the basis of artistic effect. It would not follow that the contract put Morin under no obligations whatsoever with regard to uniformity of finish. The contract expressly required it to use aluminum having “a mill finish ... to match finish ... of existing metal siding.” The jury was asked to decide whether a reasonable man would have found that Morin had used aluminum sufficiently uniform to satisfy the matching requirement. This was the right standard if, as we believe, the parties would have adopted it had they foreseen this dispute. It is unlikely that Morin intended to bind itself to a higher and perhaps unattainable standard of achieving whatever perfection of matching that General Motors’ agent insisted on, or that General Motors would have required Baystone to submit to such a standard. Because it is difficult — maybe impossible — to achieve a uniform finish with mill-finish aluminum, Morin would have been running a considerable risk of rejection if it had agreed to such a condition, and it therefore could have been expected to demand a compensating increase in the contract price. This would have required General Motors to pay a premium to obtain a freedom of action that it could not have thought terribly important, since its objective was not aesthetic. If a uniform finish was important to it, it could have gotten such a finish by specifying painted siding.

All this is conjecture; we do not know how important the aesthetics were to General Motors when the contract was signed or how difficult it really would have been to obtain the uniformity of finish it desired. The fact that General Motors accepted the replacement siding proves little, for there is evidence that the replacement siding produced the same striped effect, when viewed from an acute angle in bright sunlight, that Morin’s had. When in doubt on a difficult issue of state law it is only prudent to defer to the view of the district judge, Murphy v. White Hen Pantry Go., 691 F.2d 350, 354 (7th Cir.1982), here an experienced Indiana lawyer who thought this the type of contract where the buyer cannot unreasonably withhold approval of the seller’s performance.

Lest this conclusion be thought to strike at the foundations of freedom of contract, we repeat that if it appeared from the language or circumstances of the contract that the parties really intended General Motors to have the right to reject Morin’s work for failure to satisfy the private aesthetic taste of General Motors’ representative, the rejection would have been proper even if unreasonable. But the contract is ambiguous because of the qualifications with which the terms “artistic effect” and “decision as to acceptability” are hedged about, and the circumstances suggest that the parties probably did not intend to subject Morin’s rights to aesthetic whim.

Affirmed.

10.2 J. N. A. Realty Corp. v. Cross Bay Chelsea, Inc. 10.2 J. N. A. Realty Corp. v. Cross Bay Chelsea, Inc.

J. N. A. Realty Corp., Respondent, v Cross Bay Chelsea, Inc., Appellant, et al., Respondents.

Argued March 30, 1977;

decided June 16, 1977

Vincent F. Nicolosi and Frank M. Nicolosi for appellant.

Samuel Shapiro for respondent.

Wachtler, J.

J. N. A. Realty Corp., the owner of a building in Howard Beach, commenced this proceeding to recover possession of the premises claiming that the lease has expired. The lease grants the tenant, Cross Bay Chelsea, Inc., an option to renew and although the notice was sent, through negligence or inadvertence, it was not sent within the time prescribed in the lease. The landlord seeks to enforce the letter of the agreement. The tenant asks for equity to relieve it from a forfeiture.

The Civil Court, after a trial, held that the tenant was entitled to equitable relief. The Appellate Term affirmed, without opinion, but the Appellate Division, after granting leave, reversed and granted the petition. The tenant has appealed to this court.

Two primary questions are raised on the appeal. First, will the tenant suffer a forfeiture if the landlord is permitted to enforce the letter of the agreement. Secondly, if there will be a forfeiture, may a court of equity grant the tenant relief when the forfeiture would result from the tenant’s own neglect or inadvertence.

At the trial it was shown that J. N!. A. Realty Corp. (hereafter JNA) originally leased the premises to Victor Palermo and Sylvester Vascellaro for a 10-year term commencing on January 1, 1964. Paragraph 58 of the lease, which was attached as part of a 12-page rider, granted the tenants an option to renew for a 10-year term provided "that Tenant shall notify the landlord in writing by registered or certified mail six (6) months prior to the last day of the term of the lease that tenant desires such renewal.” The tenants opened a restaurant on the premises. In February, 1964 they formed the Foro Romano Corp. (Foro) and assigned the lease to the corporation.

By December of 1967 the restaurant was operating at a loss and Foro decided to close it down and offer it for sale or lease. In March, 1968 Foro entered into a contract with Cross Bay Chelsea, Inc. (hereafter Chelsea), to sell the restaurant and assign the lease. As a condition of the sale Foro was required to obtain a modification of the option to renew so that Chelsea would have the right to renew the lease for an additional term of 24 years.

The closing took place in June of 1968. First JNA modified the option and consented to the assignment. The modification, which consists of a separate document to be attached to the lease, states: "the Tenant shall have a right to renew this lease for a further period of Twenty-Four (24) years, instead of Ten (10) years, from the expiration of the original term of said lease * * * All other provisions of Paragraph #58 in said lease, * * * shall remain in full force and effect, except as hereinabove modified.” Foro then assigned the lease and sold its interest in the restaurant to Chelsea for $155,000. The bill of sale states that "the value of the fixtures and chattels included in this sale is the sum of $40,000 and that the remainder of the purchase price is the value of the leasehold and possession of the restaurant premises.” At that point five and one-half years remained on the original term of the lease.

In the summer of 1968 Chelsea reopened the restaurant. JNA’s president, Nicholas Arena, admitted on the stand that throughout the tenancy it regularly informed Chelsea in writing of its obligations under the lease, such as the need to pay taxes and insurance by certain dates. For instance on June 13, 1973 JNA sent a letter to Chelsea informing them that certain taxes were due to be paid. When that letter was sent the option to renew was due to expire in approximately two weeks but JNA made no mention of this. A similar letter was sent to Chelsea in September, 1973.

Arena also admitted that throughout the term of the tenancy he was "most assuredly” aware of the time limitation on the option. In fact there is some indication in the record that JNA had previously used this device in an attempt to evict another tenant. Nevertheless it was not until November 12, 1973 that JNA took any action to inform the tenant that the option had lapsed. Then it sent a letter noting that the date had passed and, the letter states, "not having heard from you as prescribed by paragraph #58 in our lease we must assume you will vacate the premises” at the expiration of the original term, January 1, 1974. By letter dated November 16, 1973 Chelsea, through its attorney, sent written notice of intention to renew the option which, of course, JNA refused to honor.

At the trial Chelsea’s principals claimed that they were not aware of the time limitation because they had never received a copy of paragraph 58 of the rider. They had received a copy of the modification but they had assumed that it gave them an absolute right to retain the tenancy for 24 years after the expiration of the original term. However, at the trial and later at the Appellate Division, it was found that Chelsea had knowledge of, or at least was "chargeable with notice” of, the time limitation in the rider and thus was negligent in failing to renew within the time prescribed.

Chelsea’s principals also testified that they had spent an additional $15,000 on improvements, at least part of which had been expended after the option had expired. Toward the end of the trial JNA’s attorney asked the court whether it would "take evidence from” Arena that he had negotiated with another tenant after the option to renew had lapsed. However, the court held that this testimony would be immaterial.

It is a settled principle of law that a notice exercising an option is ineffective if it is not given within the time specified (see, e.g., Restatement, Contracts 2d [Tent Draft No. 1, 1964], § 64, subd [b]; 1A Corbin, Contracts [1963], § 264; 1 Williston, Contracts [3d ed, 1957], § 87; Sy Jack Realty Co. v Pergament Syosset Corp., 27 NY2d 449). "At law, of course, time is always of the essence of the contract” (De Funiak, Modern Equity, § 80, p 223). Thus the tenant had no legal right to exercise the option when it did, but to say that is simply to pose the issue; it does not resolve it. Of course the tenant would not be asking for equitable relief if it could establish its rights at law.

The major obstacle to obtaining equitable relief in these cases is that default on an option usually does not result in a forfeiture. The reason is that the option itself does not create any interest in the property, and no rights accrue until the condition precedent has been met by giving notice within the time specified. Thus equity will not intervene because the loss of the option does not ordinarily result in the forfeiture of any vested rights (see, e.g., Fidelity & Columbia Trust Co. v Levin, 128 Misc 838, affd 221 App Div 786, affd 248 NY 551; Doepfner v Bowers, 55 Misc 561; cf. People’s Bank of City of N. Y. v Mitchell, 73 NY 406; but see Noyes v Anderson, 124 NY 175, 179-180, where it is indicated that the "rule may not be without exception”). The general rule is customarily stated as follows: "There is a wide distinction between a condition precedent, where no title has vested and none is to vest until the condition is performed, and a condition subsequent, operating by way of a defeasance. In the former case equity can give no relief. The failure to perform is an inevitable bar. No right can ever vest. The result is very different where the condition is subsequent. There equity will interpose and relieve against the forfeiture”. (Davis v Gray, 16 Wall [83 US] 203, 229-230.) It has been suggested that even when the option has been paid for, nothing is forfeited when it expires, because the amount paid "is the exact agreed equivalent” of the power to exercise the right for the time allotted (see 1 Corbin, Contracts, § 35, p 147).

But when a tenant in possession under an existing lease has neglected to exercise an option to renew, he might suffer a forfeiture if he has made valuable improvements on the property. This of course generally distinguishes the lease option, to renew or purchase, from the stock option or the option to buy goods. This was a distinction which some of the older cases failed to recognize (see, e.g, Fidelity & Columbia Trust Co. v Levin, supra; Doepfner v Bower, supra; cf. People’s Bank of City of N. Y. v Mitchell, supra). More recently it has been noted that "although the tenant has no legal interest in the renewal period until the required notice is given, yet an equitable interest is recognized and protected against forfeiture in some cases where the tenant has in good faith made improvements of a substantial character, intending to renew the lease, if the landlord is not harmed by the delay in the giving of the notice and the lessee would sustain substantial loss in case the lease were not renewed” (2 Pomeroy, Equity Jurisprudence [5th ed], § 453b, p 296).

The leading case on this point is Fountain Co. v Stein (97 Conn 619; 27 ALR 976) and the rule has been accepted by noted commentators (see, e.g., 1 Corbin, op. cit., § 35, p 146; 1 Williston, Contracts [3d ed], § 76, p 249, n 4; 2 Pomeroy, op. cit., § 453b, p 296). It has also been accepted and applied by this court. In Jones v Gianferante (305 NY 135, 138), citing the Fountain case we held that the tenant was entitled to "the benefit of the rule or practice in equity which relieves against such forfeitures of valuable lease terms when default in notice has not prejudiced the landlord, and has resulted from an honest mistake, or similar excusable fault.” The rule was extended in Sy Jack Realty Co. v Pergament Syosset Corp. (27 NY2d 449, 453, supra) to preserve the tenant’s interest in a "long-standing location for a retail business” because this is "an important part of the good will of that enterprise, [and thus] the tenant stands to lose a substantial and valuable asset.”

In neither of those cases were we asked to consider whether the tenant would be entitled to equitable relief from the consequences of his own neglect or "mere forgetfulness” as the court had held in the Fountain case (supra). In Gianferante the default was due to an ambiguous lease, and in Sy Jack the notice was mailed but never delivered (but see Roy’s of North Syracuse v P & C Food Markets, 51 AD2d 641, mot for lv to app den 38 NY2d 711; and the dissenting opn in Sy Jack [supra, p 456, n 1], where it is noted that the three cases cited in Williston—the principle one being the Fountain case—"obviously warranted equitable relief. For not only in those cases was there 'excusable fault’, but also in each one the tenant had made substantial improvements”). But the principle involved is well established in this State. A tenant or mortgagor should not be denied equitable relief from the consequences of his own neglect or inadvertence if a forfeiture would result (Giles v Austin, 62 NY 486; Noyes v Anderson, 124 NY 175; Roy’s of North Syracuse v P & C Food Markets, supra; see, also, 2 Pomeroy, Equity Jurisprudence [5th ed], § 452, p 287). The rule applies even though the tenant or mortgagor, by his inadvertence, has neglected to perform an affirmative duty and thus breached a covenant in the agreement (Giles v Austin, supra; Noyes v Anderson, supra).

On occasion the court has cautioned that equitable relief would be denied where there has been a willful or gross neglect (Noyes v Anderson, supra, p 179), but it has been reluctant to employ the sanction when a forfeiture would result. In Giles v Austin (supra, p 491), for instance, the landlord sought to recover possession of the premises after the tenant had neglected to pay the taxes as required by a covenant in the lease. We held that although the tenant had not paid the taxes since the inception of the lease in 1859, and had only paid them after suit-was commenced in 1868, the tenant’s default was not "so willful, or his neglect so inexcusable, that a court of equity should have denied him any relief.”

There are several cases in which this court has denied a tenant or mortgagor equitable relief because of his own neglect to perform within the time fixed in the lease or mortgage, but only when it has found that there was "no penalty, no forfeiture” (Graf v Hope Bldg. Corp., 254 NY 1, 4; Fidelity & Columbia Trust Co. v Levin, 128 Misc 838, affd 221 App Div 786, affd 248 NY 551, supra; People’s Bank of City ofN.Y.v Mitchell, 73 NY 406, supra). Cardozo took a different view. He felt that even though there may be no penalty or forfeiture "in a strict or proper sense” equity should "relieve against it if default has been due to mere venial inattention and if relief can be granted without damage to the lender”. Even in those cases he would apply the general equitable principle that "the gravity of the fault must be compared with the gravity of the hardship” (Graf v Hope Bldg. Corp., supra, pp 9-10, 13 [Cardozo, Ch. J., dissenting]; see, also, 2 Pomeroy, Equity Jurisprudence [5th ed], § 439, p 220).

Here, as noted, the tenant has made a considerable investment in improvements on the premises—$40,000 at the time of purchase, and an additional $15,000 during the tenancy. In addition, if the location is lost, the restaurant would undoubtedly lose a considerable amount of its customer good will. The tenant was at fault, but not in a culpable sense. It was, as Cardozo says, "mere venial inattention.” There would be a forfeiture and the gravity of the loss is certainly out of all proportion to the gravity of the fault. Thus, under the circumstances of this case, the tenant would be entitled to equitable relief if there is no prejudice to the landlord.

However it is not clear from the record whether JNA would be prejudiced if the tenant is relieved of its default. Because of the trial court’s ruling, JNA was unable to submit proof that it might be prejudiced if the terms of the agreement were not enforced literally. Its proof of other negotiations was considered immaterial. It may be that after the tenant’s default the landlord, relying on the agreement, in good faith, made other commitments for the premises. But if JNA did not rely on the letter of the agreement then, it should not be permitted to rely on it now to exact a substantial forfeiture for the tenant’s unwitting default. This, however, must be resolved at a new trial.

Finally we would note, as the dissenters do, that it is possible to imagine a situation in which a tenant holding an option to renew might intentionally delay beyond the time prescribed in order to exploit a fluctuating market. However, as the dissenters also note, there is no evidence to suggest that that is what occurred here. On the contrary there has been an affirmed finding of fact that the tenant’s late notice was due to negligence. Of course a tenant who has intentionally delayed should not be relieved of a forfeiture simply because this tenant, who was merely inadvertent, may be granted equitable relief. But, on the other hand, we do not believe that this tenant, or any tenant, guilty only of negligence should be denied equitable relief because some other tenant, in some other case, may be found to have acted in bad faith. By its nature equitable relief must always depend on the facts of the particular case and not on hypotheticals.

Accordingly, the order of the Appellate Division should be reversed and a new trial granted.

Chief Judge Breitel (dissenting).

Relieving the tenant of its negligent failure to exercise its option to renew a lease within the prescribed time upsets established precedent, introduces instability in business transactions, and disregards commercial realities. I therefore dissent.

This case involves an option to renew a lease, not a mortgage foreclosure or an acceleration clause in a lease or mortgage. The categories and applicable precedents are not to be confused.

In a summary holdover proceeding brought by J. N. A. Realty, a landlord, to recover possession of leased commercial premises, tenant, Cross Bay Chelsea, appeals. The Civil Court’s dismissal of the petition, after trial, was affirmed at Appellate Term, but the Appellate Division reversed, one Justice dissenting, and awarded the landlord possession.

At issue is the availability of equitable relief to remedy a commercial tenant’s failure, by the appointed date, to exercise its option to renew a lease when the only explanation is sheer negligence.

The order of the Appellate Division should be affirmed, and the landlord awarded possession. Mere negligence does not justify departing from the rule that notice of intention to exercise an option to renew must be given within the prescribed period. Equitable relief is never justified by the fact alone, always present, that the tenant will suffer some sort of economic detriment.

The record is unusually deficient in many respects. From it, however, may be culled what follows.

In December, 1963, J. N. A. Realty, as owner, leased a newly erected commercial building in Queens County to Victor Palermo and Sylvester Vascellero. The lease agreement consisted of a printed form and a single 12-page rider. According to the rider, the lease extended for 10 years, to begin January 1, 1964, with an option for an additional 10-year term. All that was required, as set forth in paragraph 58 of the 12-page rider, was that the "tenant * * * notify the landlord in writing by registered or certified mail six (6) months prior to the last day of the term of the lease that tenant desires such renewal.”

Shortly thereafter, Palermo and Vascellero assigned the lease to Foro Romano, Inc., a restaurant corporation in which they were the principals. But the restaurant operated at a loss. By late 1967, following undescribed attempts by others, not identified, at the behest of the tenant, and with six years remaining on the initial term, the business was closed down. It was not until February, 1968 that Peter and John Morfogen, principals of the present tenant Cross Bay Chelsea, responded to an advertisement in the New York Times and indicated their interest in purchasing the leasehold and the closed-down business.

The precise details of the initial conversations between the parties cannot be extracted from the record because they are included only in bits and pieces. Apparently, however, the prospective buyer, who at the time of trial was operating four other restaurants in Manhattan, Queens, and Nassau County, was ready to agree only if a 30-year lease could be arranged. To that effect, a meeting of the principals of landlord J. N. A, Foro, and Chelsea was held on March 16, 1968, and a "modification and extension of lease” agreement executed. While the modification agreement provided that the tenant have the "right to renew this lease for a further period of Twenty-Four (24) years, instead of Ten (10) years”, it also continued in full force and effect "[a]ll other provisions of Paragraph #58”, which contained the requirement of six months’ notice of election of the option to renew. The modified lease provided that a portion of the taxes and insurance premiums, and all of the interior repairs, be borne by the tenant. The starting rent reserved in the option was $1,000 per month.

J. N. A.’s principals attended this critical meeting without counsel, although the Chelsea principals, who now claim ignorance of the conditions to exercising the 24-year renewal option, were accompanied by their lawyer and an accountant. The transaction eventually involved a gross price of $155,000, much of it deferred, for the restaurant, fixtures, and the assignment of the leasehold. Of the $155,000, $40,000 was allocated to the chattels and fixtures, and the balance to the leasehold. Chelsea’s lawyer also attended the June 8 closing of the transfer of the modified lease and the sale of the restaurant, following the March 16 lease modification meeting. Between the closing of the lease modification agreement in March, 1968 and the final closing in June, 1968, Chelsea arranged for a liquor license. Also before the June, 1968 closing, Chelsea had invested $15,000 in undescribed improvements in the premises. In short order the restaurant was reopened and was quite successful, or else this litigation would never have ensued.

On July 1, 1973, the date the renewal option was to be exercised, no notice or advice of any kind was sent or given to the landlord. It was not until November 16, 1973, some four and a-half months later, that Chelsea, in response to a letter from J. N. A., sent to the landlord a purported notice to exercise the option. J. N. A. refused to recognize the notice, and on March 4, 1974 instituted this holdover proceeding. The record is silent about the intervening period except to indicate that there were negotiations.

To excuse its failure to send a renewal notice by the July 1 deadline and to support a claim to equitable relief, Chelsea asserts that it never received a copy of the 12-page rider attached to the original lease. In addition to the 1968 modification agreement’s reference to the 1963 rider, the entire lease, including that rider, was filed in April, 1968 with the Division of Alcoholic Beverage Control on Chelsea’s preclosing application for a liquor license. While Chelsea contends that the 1963 rider found in the agency’s file must have been taken from an earlier application submission, the trial court resolved this issue of fact in favor of the landlord. The Appellate Division expressly found that Chelsea had knowledge, or at least should be chargeable with notice, of the provisions of paragraph 58 of the 1963 rider requiring six months’ notice to renew.

Chelsea contends that J. N. A.’s representative was on the premises in the summer of 1973, after law day had passed, and failed to comment when he saw that additional improvements were still being made. There is no evidence of what these improvements were, how extensive they were, their value, or whether they were fixed or movable fixtures or equipment. J. N. A. never conceded that the visits had occurred or that such post law day improvements had been made.

Had an honest mistake or similar "excusable fault”, as opposed to what is undoubtedly mere carelessness, occasioned the tenant’s tardiness, absent prejudice to the landlord, equitable relief would be available (e.g., Sy Jack Realty Co. v Pergament Syosset Corp., 27 NY2d 449, 453; Jones v Gianferante, 305 NY 135, 138). At issue, instead, is the availability of equitable relief where the only excuse for the commercial tenant’s dilatory failure to exercise its option to renew is sheer carelessness.

Enough has been said to uncover a common situation. Experienced and even hardened businessmen at cross-purposes over the renewal of a valuable lease term seek on the one hand to stand by the written agreement, and on the other, to loosen the applicable rules to receive ad hoc adjustment of equities and relief from economic detriment. The landlord wants a higher return. The tenant wants to keep the old bargain. Which of the profit-seeking parties in this particular case should prevail as a matter of morals is not within the province of the courts. The well-settled doctrine is that with respect to options, whether they be lease renewal options, options to purchase real or personal property, or stock options, time is of the essence. The exceptions, namely, estoppel, fraud, mistake, accident, or overreaching, are few. Commercial stability and certainty are paramount, and always the dangers of unsolvable issues of fact and speculative manipulation (as with stock options) are to be avoided.

The landlord should be awarded possession of the premises in accordance with the undisputed language and manifested intention of the written lease, its 12-page rider, and modification. It does not suffice that the tenant may suffer an economic detriment in losing the renewal period. Nor does it suffice that the delay in giving notice may have caused the landlord no "prejudice”, other than loss of the opportunity to relet the property or renegotiate the terms of a lease on a fresh basis. Once an option to renew a lease has been conditioned upon the tenant’s giving timely notice, the commercial lessee should not be heard to complain that through carelessness a valued asset has been lost, anymore than one would allow the landlord to complain of the economic detriment to him in agreeing to an improvident option to renew.

The court unanimously accepts the general rule at law: an option to renew a commercial lease must be exercised within the appointed time period (e.g., Sy Jack Realty Co. v Pergament Syosset Corp., 27 NY2d 449, 452, supra,' and authorities cited; see Restatement, Contracts 2d [Tent Draft Nos. 1-7, 1973], § 64, Comment f; 34 NY Jur, Landlord and Tenant, §§ 418-419; 51C CJS, Landlord and Tenant, § 59). Underlying the bar to equitable relief is the theory that until the condition precedent is fulfilled, that is, until the required timely notice is given, there is no "forfeiture” for which equity will extend protection (Fidelity & Columbia Trust Co. v Levin, 128 Misc 838, 844-845, affd 221 App Div 786, affd 248 NY 551; 2 Pomeroy, Equity Jurisprudence [5th ed], § 453b, p 296). While the rule has been bolstered by traditional concepts of estates in land, its basis has current commercial and economic validity.

In this State, as in others, relief has been afforded tenants threatened with loss of an expected renewal period (see, generally, Effect of Lessee’s Failure or Delay in Giving Notice Within Specified Time, of Intention to Renew Lease, Ann., 44 ALR2d 1359, esp 1362-1369). But in New York, as elsewhere, the circumstances conditioning such relief have been carefully limited. It is only where the tenant can show, not mere negligence, but an excuse such as fraud, mistake, or accident, that is, one or more of the categories common and integral to invocation of equity, that courts have, despite the literal agreement and intention of the parties, stepped in to prevent a loss (see, e.g., Jones v Gianferante, 305 NY 135, 138-139, supra; 1 McAdam, Landlord and Tenant [5th ed], § 156, pp 721-722).

Even in the case of excusable default by the tenant the court looks to the investment the tenant has made to bolster his right to equitable relief. But the fact of tenant investment alone is not enough to justify intervention. Thus, in the leading cases excusing the tenant’s late notice, mention is perforce made of investments and improvements (e.g., Sy Jack Realty Co. v Pergament Syosset Corp., 27 NY2d 449, 453, supra; Jones v Gianferante, 305 NY 135, 138, supra). But the loss or "forfeiture” of these investments was not alone the trigger to granting relief. Indispensable is the existence of some mistake or excusable default. Thus, in Jones v Gianferante (supra, p 138), an ambiguous term in the lease excused the tenant’s failure. And in Sy Jack v Pergament (supra, p 453), it was reliance on the post office to deliver the notice, mailed three days before law day, that was forgiven. In no case of accepted or acceptable authority, however, were improvements alone enough to help the negligent tenant.

The majority facilely disposes of the tenant’s delinquency in exercising its option by relying on cases in which a party, notwithstanding its negligence, was relieved from a forfeiture (e.g., Giles v Austin, 62 NY 486, 493-494, a conditional limitation in a lease; Noyes v Anderson, 124 NY 175, 182-183, mortgagor’s failure to pay an assessment). But indiscriminate application of principles evolved to deal with mortgage foreclosures or a lessor’s right to re-enter upon a tenant’s failure to pay taxes and assessments when due does not withstand analysis. Since ever so long, enforcement of a mortgage has rested in equity (see Jamaica Sav. Bank v M. S. Investing Co., 274 NY 215, 219; 38 NY Jur, Mortgages and Deeds of Trust, § 317). It is also significant that as to foreclosure, time is not of the essence (see 10 NY Jur, Contracts, § 270). Even where acceleration clauses are involved and a strong argument can be made for allowing relief, time has been of the essence and negligence has not been excused (see Graf v Hope Bldg. Corp., 254 NY 1, 4, 7 [dissenting opn. per Cardozo, Ch. J.]). It is equally inappropriate to analogize to a lessee’s failure to comply with a lease requirement that taxes and assessments be paid as they become due (see Giles v Austin, supra, pp 493-494). For the loss of an existing lease term subject to a condition subsequent distinguishes that situation from the loss of a possible option period subject to a condition precedent. An option is a right to purchase or acquire an interest in personal or real property in the future, and, if precise, it carries an invulnerable requirement to comply with all conditions, including that of time which is therefore of the essence in law and equity.

There are cases, not binding on this court, which express the principles discussed. For reasons that are not persuasive they would distinguish, however, between mere neglect or forgetfulness and gross or willful negligence, whatever that might be (see Fountain Co. v Stein, 97 Conn 619, 626-627; Xanthakey v Hayes, 107 Conn 459, 469; see, generally, 1 Williston, Contracts [3d ed], § 76, p 249, n 4). This is not a distinction generally accepted and is hardly a pragmatic one to apply in an area where the opportunities for distortion and manipulation are so great. The instability and uncertainty would be dangerous and would allow for ad hoc dispensations in particular cases without reliable rule so essential to commercial enterprise.

To begin with, under the guise of sheer inadvertence, a tenant could gamble with a fluctuating market, at the expense of his landlord, by delaying his decision beyond the time fixed in the agreement. The market having resolved in favor of exercising the option, the landlord, even though the day appointed in the agreement has passed, could be held to the return set out in the option, although if the market had resolved otherwise, the tenant could not be held to the renewal period.

None of this is to say that the tenant in this case was guilty of any manipulation. Hardly so. But what the court is concerned with is a rule for this case which perforce must cover other cases of like kind, where there will be no assurance that the "forgetfulness” is no more than that. The worst of the matter is that the kind of paltry record made in this case is hardly one on which a new rule with potential for mischief should be based. When the option, especially one requiring notice well in advance of the expiration of the lease, permits of economic manipulation, in commercial fairness the parties, especially if represented by counsel, should be held to their bargain, if plainly expressed.

Considering investments in the premises or the renewal term a "forfeiture” as alone warranting equitable relief would undermine if not dissolve the general rule upon which there is agreement. For, it is difficult to imagine a dilatory commercial tenant, particularly one in litigation over a renewal, who would not or could not point, scrupulously or unscrupulously, to some threatened investment in the premises, be it a physical improvement or the fact of good will. As a practical matter, it is not unreasonable to expect the commercial tenant, as compared with his residential counterpart, to protect his business interests with meticulousness, a meticulousness to which he would hold his landlord. All he, or his lawyer, need do is red-flag the date on which he has to act.

Having established no excuse, other than its own carelessness, Chelsea’s claim is unfounded. Even if Chelsea honestly thought it enjoyed a 30-year lease, it does not change the result. Nor is it helpful to argue that Chelsea, always represented by a lawyer, was unable to procure a copy of the entire lease agreement. Indeed, it borders on the utterly incredible that experienced, sophisticated businessmen and their lawyers would not have assembled and scrutinized every relevant document affecting a long-term lease covering, with a renewal, a 30-year period.

That adherence to well-settled principles, like a Statute of Limitations or a Statute of Frauds, works a hardship on some does not, alone, permit a court to depart from sound doctrine and principles. Even if precedent did not control the same doctrines and principles discussed should be applied.

Accordingly, I dissent and vote that the order of the Appellate Division should be affirmed, and the landlord awarded possession of the premises.

Judges Gabrielli, Fuchsberg and Cooke concur with Judge Wachtler; Chief Judge Breitel dissents and votes to affirm in a separate opinion in which Judges Jasen and Jones concur.

Order reversed, with costs, and a new trial granted.

10.3 Jacob & Youngs, Inc. v. Kent. (PART I) 10.3 Jacob & Youngs, Inc. v. Kent. (PART I)

230 N.Y. 239
129 N.E. 889

JACOB & YOUNGS, Inc.,

v.

KENT.

Court of Appeals of New York.
Jan. 25, 1921.

Action by Jacob & Youngs, Incorporated, against George E. Kent. From an order of the Appellate Division (187 App. Div. 100,175 N. Y. Supp. 281), reversing judgment for defendant entered on verdict directed by the court and granting new trial, defendant appeals.

Order affirmed and judgment absolute directed in favor of plaintiff.

McLaughlin, Pound, and Andrews, JJ., dissenting. [890]
[230 N.Y. 239]Appeal from Supreme Court, Appellate Division, First department.
[230 N.Y. 240]Henry W. Hardon, of New York City, for appellant.

Frederick Hulse and Cornelius J. Sullivan, Jr., both of New York City, for respondent.

 

CARDOZO, J.

 

The plaintiff built a country residence for the defendant at a cost of upwards of $77,000, and now sues to recover a balance of $3,483.46, remaining unpaid. The work of construction ceased in June, 1914, and the defendant then began to occupy the dwelling. There was no complaint of defective performance until March, 1915. One of the specifications for the plumbing work provides that--

‘All wrought-iron pipe must be well galvanized, lap welded pipe of the grade known as ‘standard pipe’ of Reading manufacture.'

The defendant learned in March, 1915, that some of the pipe, instead of being made in Reading, was the product of other factories. The plaintiff was accordingly directed by the architect to do the work anew. The plumbing was then encased within the walls except in a few places where it had to be exposed. Obedience to the order meant more than the substitution of other pipe. It meant the demolition at great expense of substantial parts of [230 N.Y. 241]the completed structure. The plaintiff left the work untouched, and asked for a certificate that the final payment was due. Refusal of the certificate was followed by this suit.

The evidence sustains a finding that the omission of the prescribed brand of pipe was neither fraudulent nor willful. It was the result of the oversight and inattention of the plaintiff's subcontractor. Reading pipe is distinguished from Cohoes pipe and other brands only by the name of the manufacturer stamped upon it at intervals of between six and seven feet. Even the defendant's architect, though he inspected the pipe upon arrival, failed to notice the discrepancy. The plaintiff tried to show that the brands installed, though made by other manufacturers, were the same in quality, in appearance, in market value, and in cost as the brand stated in the contract-that they were, indeed, the same thing, though manufactured in another place. The evidence was excluded, and a verdict directed for the defendant. The Appellate Division reversed, and granted a new trial.

[1] We think the evidence, if admitted, would have supplied some basis for the inference that the defect was insignificant in its relation to the project. The courts never say that one who makes a contract fills the measure of his duty by less than full performance. They do say, however, that an omission, both trivial and innocent, will sometimes be atoned for by allowance of the resulting damage, and will not always be the breach of a condition to be followed by a forfeiture. Spence v. Ham, 163 N. Y. 220, 57 N. E. 412,51 L. R. A. 238; Woodward v. Fuller, 80 N. Y. 312; Glacius v. Black, 67 N. Y. 563, 566;Bowen v. Kimbell, 203 Mass. 364, 370, 89 N. E. 542,133 Am. St. Rep. 302. The distinction is akin to that between dependent and independent promises, or between promises and conditions. Anson on Contracts (Corbin's Ed.) § 367; 2 Williston on Contracts, § 842. Some promises are so plainly independent that they can never [230 N.Y. 242]by fair construction be conditions of one another. Rosenthal Paper Co. v. Nat. Folding Box & Paper Co., 226 N. Y. 313, 123 N. E. 766;Bogardus v. N. Y. Life Ins. Co., 101 N. Y. 328, 4 N. E. 522. Others are so plainly dependent that they must always be conditions. Others, though dependent and thus conditions when there is departure in point of substance, will be viewed as independent and collateral when the departure is insignificant. 2 Williston on Contracts, §§ 841, 842; Eastern Forge Co. v. Corbin, 182 Mass. 590, 592, 66 N. E. 419; Robinson v. Mollett, L. R., 7 Eng. & Ir. App. 802, 814; Miller v. Benjamin, 142 N. Y. 613, 37 N. E. 631. Considerations partly of justice and partly of presumable intention are to tell us whether this or that promise shall be placed in one class or in another. The simple and the uniform will call for different remedies from the multifarious and the intricate. The margin of departure within the range of normal expectation upon a sale of common chattels will vary from the margin to be expected upon a contract for the construction of a mansion or a ‘skyscraper.’ There will be harshness sometimes and oppression in the implication of a condition when the thing upon which labor has been expended is incapable of surrender because united to the land, and equity and reason in the implication of a like condition when the subject-matter, if defective, is in shape to be returned. From the conclusion that promises may not be treated as dependent to the extent of their uttermost minutiae without a sacrifice of justice, the progress is a short one to the conclusion that they may not be so treated without a perversion of intention. Intention not otherwise revealed may be presumed to hold in contemplation the reasonable and probable. If something else is in view, it must not be left to implication. There will be no assumption of a purpose to visit venial faults with oppressive retribution.

Those who think more of symmetry and logic in the development of legal rules than of practical adaptation to the attainment of a just result will be troubled by a classification[230 N.Y. 243]where the lines of division are so wavering and blurred. Something, doubtless, may be said on the score of consistency and certainty in favor of a stricter standard. The courts have balanced such considerations against those of equity and fairness, and found the latter to be the weightier. The decisions in this state commit us to the liberal view, which is making its way, nowadays, in jurisdictions slow to welcome it. Dakin & Co. v. Lee, 1916, 1 K. B. 566, 579. Where the line is to be drawn between the important and the trivial cannot be settled by a formula. ‘In the nature of the case precise boundaries are impossible.’ 2 Williston on Contracts, § 841. The same omission may take on one aspect or another according to its setting. Substitution of equivalents may not have the same significance in fields of art on the one side and in those of mere utility on the other. Nowhere will change be tolerated, however, if it is so dominant or pervasive as in any real or substantial measure to frustrate the purpose of the contract. Crouch v. Gutmann, 134 N. Y. 45, 51,31 N. E. 271,30 Am. St. Rep. 608. There is no general license to install whatever, in the builder's judgment, may be regarded as ‘just as good.’ Easthampton L. & C. Co., Ltd., v. Worthington, 186 N. Y. 407, 412,79 N. E. 323. The question is one of degree, to be answered, if there is doubt, by the triers of the facts (Crouch v. Gutmann; Woodward v. Fuller, supra), and, if the inferences are certain, by the judges of the law (Easthampton L. & C. Co., Ltd., v. Worthington, supra). We must weigh the purpose to be served, the desire to be gratified, the excuse for deviation from the letter, the cruelty of enforced adherence. Then only can we tell whether literal fulfillment is to be implied by law as a condition. This is not to say that the parties are not free by apt and certain words to effectuate a purpose that performance of every term shall be a condition of recovery. That question is not here. This is merely to say that the law will be slow to impute the purpose, in the silence of the parties, where the significance [230 N.Y. 244]of the default is grievously out of proportion to the oppression of the forfeiture. The willful transgressor must accept the penalty of his transgression. Schultze v. Goodstein, 180 N. Y. 248, 251,73 N. E. 21;Desmond-Dunne Co. v. Friedman-Doscher Co., 162 N. Y. 486, 490,56 N. E. 995. For him there is no occasion to mitigate the rigor of implied conditions. The transgressor whose default is unintentional and trivial may hope for mercy if he will offer atonement for his wrong. Spence v. Ham, supra.

[2] In the circumstances of this case, we think the measure of the allowance is not the cost of replacement, which would be great, but the difference in value, which would be either nominal or nothing. Some of the exposed sections might perhaps have been replaced at moderate expense. The defendant did not limit his demand to them, but treated the plumbing as a unit to be corrected from cellar to roof. In point of fact, the plaintiff never reached the stage at which evidence of the extent of the allowance became necessary. The trial court had excluded evidence that the defect was unsubstantial, and in view of that ruling there was no occasion for the plaintiff to go farther with an offer of proof. We think, however, that the offer, if it had been made, would not of necessity have been defective because directed to difference in value. It is true that in most cases the cost of replacement is the measure. Spence v. Ham, supra. The owner is entitled to the money which will permit him to complete, unless the cost of completion is grossly and unfairly out of proportion to the good to be attained. When that is true, the measure is the difference in value. Specifications call, let us say, for a foundation built of granite quarried in Vermont. On the completion of the building, the owner learns that through the blunder of a subcontractor part of the foundation has been built of granite of the same quality quarried in New Hampshire. The measure of allowance is not the cost of reconstruction. ‘There may be [230 N.Y. 245]omissions of that which could not afterwards be supplied exactly as called for by the contract without taking down the building to its foundations, and at the same time the omission may not affect the value of the building for use or otherwise, except so slightly as to be hardly appreciable.’ Handy v. Bliss, 204 Mass. 513, 519, 90 N. E. 864,134 Am. St. Rep. 673. Cf. Foeller v. Heintz, 137 Wis. 169, 178, 118 N. W. 543,24 L. R. A. (N. S.) 321; [892] Oberlies v. Bullinger, 132 N. Y. 598, 601,30 N. E. 999; 2 Williston on Contracts, § 805, p. 1541. The rule that gives a remedy in cases of substantial performance with compensation for defects of trivial or inappreciable importance has been developed by the courts as an instrument of justice. The measure of the allowance must be shaped to the same end.

The order should be affirmed, and judgment absolute directed in favor of the plaintiff upon the stipulation, with costs in all courts.

McLAUGHLIN, J.

 

I dissent. The plaintiff did not perform its contract. Its failure to do so was either intentional or due to gross neglect which, under the uncontradicted facts, amounted to the same thing, nor did it make any proof of the cost of compliance, where compliance was possible.

Under its contract it obligated itself to use in the plumbing only pipe (between 2,000 and 2,500 feet) made by the Reading Manufacturing Company. The first pipe delivered was about 1,000 feet and the plaintiff's superintendent then called the attention of the foreman of the subcontractor, who was doing the plumbing, to the fact that the specifications annexed to the contract required all pipe used in the plumbing to be of the Reading Manufacturing Company. They then examined it for the purpose of ascertaining whether this delivery was of that manufacture and found it was. Thereafter, as pipe was required in the progress of the work, the foreman of the subcontractor would leave word at its [230 N.Y. 246]shop that he wanted a specified number of feet of pipe, without in any way indicating of what manufacture. Pipe would thereafter be delivered and installed in the building, without any examination whatever. Indeed, no examination, so far as appears, was made by the plaintiff, the subcontractor, defendant's architect, or any one else, of any of the pipe except the first delivery, until after the building had been completed. Plaintiff's architect then refused to give the certificate of completion, upon which the final payment depended, because all of the pipe used in the plumbing was not of the kind called for by the contract. After such refusal, the subcontractor removed the covering or insulation from about 900 feet of pipe which was exposed in the basement, cellar, and attic, and all but 70 feet was found to have been manufactured, not by the Reading Company, but by other manufacturers, some by the Cohoes Rolling Mill Company, some by the National Steel Works, some by the South Chester Tubing Company, and some which bore no manufacturer's mark at all. The balance of the pipe had been so installed in the building that an inspection of it could not be had without demolishing, in part at least, the building itself.

I am of the opinion the trial court was right in directing a verdict for the defendant. The plaintiff agreed that all the pipe used should be of the Reading Manufacturing Company. Only about two-fifths of it, so far as appears, was of that kind. If more were used, then the burden of proving that fact was upon the plaintiff, which it could easily have done, since it knew where the pipe was obtained. The question of substantial performance of a contract of the character of the one under consideration depends in no small degree upon the good faith of the contractor. If the plaintiff had intended to, and had, complied with the terms of the contract except as to minor omissions, due to inadvertence, then he might be allowed to recover the contract price, less the amount [230 N.Y. 247]necessary to fully compensate the defendant for damages caused by such omissions. Woodward v. Fuller, 80 N. Y. 312; Nolan v. Whitney, 88 N. Y. 648. But that is not this case. It installed between 2,000 and 2,500 feet of pipe, of which only 1,000 feet at most complied with the contract. No explanation was given why pipe called for by the contract was not used, nor that any effort made to show what it would cost to remove the pipe of other manufacturers and install that of the Reading Manufacturing Company. The defendant had a right to contract for what he wanted. He had a right before making payment to get what the contract called for. It is no answer to this suggestion to say that the pipe put in was just as good as that made by the Reading Manufacturing Company, or that the difference in value between such pipe and the pipe made by the Reading Manufacturing Company would be either ‘nominal or nothing.’ Defendant contracted for pipe made by the Reading Manufacturing Company. What his reason was for requiring this kind of pipe is of no importance. He wanted that and was entitled to it. It may have been a mere whim on his part, but even so, he had a right to this kind of pipe, regardless of whether some other kind, according to the opinion of the contractor or experts, would have been ‘just as good, better, or done just as well.’ He agreed to pay only upon condition that the pipe installed were made by that company and he ought not to be compelled to pay unless that condition be performed. Schultze v. Goodstein, 180 N. Y. 248, 73 N. E. 21; Spence v. Ham, supra; Steel S. & E. C. Co. v. Stock, 225 N. Y. 173, 121 N. E. 786;Van Clief v. Van Vechten, 130 N. Y. 571, 29 N. E. 1017;Glacius v. Black, 50 N. Y. 145, 10 Am. Rep. 449;Smith v. Brady, 17 N. Y. 173, and authorities cited on [893] page 185, 72 Am. Dec. 442. The rule, therefore, of substantial performance, with damages for unsubstantial omissions, has no application. Crouch v. Gutmann, 134 N. Y. 45, 31 N. E. 271,30 Am. St. Rep. 608;Spence v. Ham, 163 N. Y. 220, 57 N. E. 412,51 L. R. A. 238.

[230 N.Y. 248]What was said by this court in Smith v. Brady, supra, is quite applicable here:

‘I suppose it will be conceded that every one has a right to build his house, his cottage or his store after such a model and in such style as shall best accord with his notions of utility or be most agreeable to his fancy. The specifications of the contract become the law between the parties until voluntarily changed. If the owner prefers a plain and simple Doric column, and has so provided in the agreement, the contractor has no right to put in its place the more costly and elegant Corinthian. If the owner, having regard to strength and durability, has contracted for walls of specified materials to be laid in a particular manner, or for a given number of joists and beams, the builder has no right to substitute his own judgment or that of others. Having departed from the agreement, if performance has not been waived by the other party, the law will not allow him to allege that he has made as good a building as the one he engaged to erect. He can demand payment only upon and according to the terms of his contract, and if the conditions on which payment is due have not been performed, then the right to demand it does not exist. To hold a different doctrine would be simply to make another contract, and would be giving to parties an encouragement to violate their engagements, which the just policy of the law does not permit.’ (17 N. Y. 186, 72 Am. Dec. 422).

I am of the opinion the trial court did not err in ruling on the admission of evidence or in directing a verdict for the defendant.

For the foregoing reasons I think the judgment of the Appellate Division should be reversed and the judgment of the Trial Term affirmed.

HISCOCK, C. J., and HOGAN and CRANE, JJ., concur with CARDOZO, J.

 

POUND and ANDREWS, JJ., concur with McLAUGHLIN, J.


 

Order affirmed, etc.

10.4 Sackett v. Spindler 10.4 Sackett v. Spindler

[Civ. No. 23343.

First Dist., Div. One.

Jan. 30, 1967.]

SHELDON SACKETT, Plaintiff, Cross-defendant and Appellant, v. PAUL R. SPINDLER, Defendant, Cross-complainant and Respondent.

*224Vincent Hallman, Carl B. Shapiro, Patrick Sarsfield Hallinan and LeRoy W. Rice for Plaintiff, Cross-defendant and Appellant.

Kahle, Adams & Ever ton and Douglass M. Adams for Defendant, Cross-complainant and Respondent.

MOLINARI, P. J.

Plaintiff and cross-defendant, Sheldon Sackett, appeals from the judgment of the trial court determining that he take nothing on his complaint for money had and received and further awarding defendant and cross-complainant, Paul Spindler, $34,575.74 plus interest on his cross-complaint against Sackett for breach of contract. Sackett’s contentions on appeal are as follows: (1) the evidence reveals no “actionable breach” on his part; (2) damages were ineor*225rectly computed; (3) certain evidence was improperly excluded; (4) the trial court’s findings as to mitigation of damages by Spindler are not supported by the evidence; and (5) the trial court erred in awarding interest to Spindler.

The Record

As of July 8, 1961 Spindler was the owner of a majority of the shares of S & S Newspapers, a corporation which, since April 1, 1959, had owned and operated a newspaper in Santa Clara known as the Santa Clara Journal. In addition, Spindler, as president of S & S Newspapers, served as publisher, editor, and general manager of the Journal. On July 8, 19611 Spindler entered into a written agreement with Saekett whereby the latter agreed to purchase 6,316 shares of stock in S & S Newspapers, this number representing the total number of shares outstanding. The contract provided for a total purchase price of $85,000 payable as follows: $6,000 on or before July 10, $20,000 on or before July 14, and $59,000 on or before August 15. In addition the agreement obligated Saekett to pay interest at the rate of 6 percent on any unpaid balance. And finally, the contract provided for delivery of the full amount of stock to Sackett free of encumbrances when he made his final payment under the contract.

Sackett paid the initial $6,000 installment on time and made an additional $19,800 payment on July 21. On August 10 Sackett gave Spindler a check for the $59,200 balance due under the contract; however, due to the fact that the account on which this check was drawn contained insufficient funds to cover the check, the check was never paid. Meanwhile, however, Spindler had acquired the stock owned by the minority shareholders of S & S Newspapers, had endorsed the stock certificates, and had given all but 454 shares to Sackett’s attorneys to hold in escrow until Sackett had paid Spindler the $59,200 balance due under the contract. However, on September 1, after the $59,200 cheek had not cleared, Spindler reclaimed the stock certificates held by Sackett’s attorney.

Thereafter, on September 12 Spindler received a telegram from Sackett to the effect that the latter “had secured payments our transaction and was ready, willing and eager to transfer them” and that Saekett’s new attorney would contact Spindler’s attorney. In response to this telegram Spindler, by return telegram, gave Sackett the name of Spindler’s attorney. Subsequently, Sackett’s attorney contacted Spind*226ler’s attorney and arranged a meeting to discuss Sackett’s performance of the contract. At this meeting, which was held on September 19 at the office of Sackett’s attorney, in response to Sackett’s representation that he would be able to pay Spindler the balance due under the contract by September 22, Spindler served Saekett with a notice to the effect that unless the latter paid the $59,200 balance due under the contract plus interest by that date, Spindler would not consider completing the sale and would assess damages for Sackett’s breach of the agreement. Also discussed at this meeting was the newspaper’s urgent need for working capital. Pursuant to this discussion Saekett on the same date paid Spindler $3,944.26 as an advance for working capital. However, Saekett failed to make any further payments or to communicate with Spindler by September 22, and on that date the latter, by letter addressed to Saekett, again extended the time for Sackett’s performance until September 29. Again Saekett failed to tender the amount owing under the contract or to contact Spindler by that date, the next communication between the parties occurring on October 4 in the form of a telegram by which Saekett advised Spindler that Sackett’s assets were now free as a result of the fact that his wife’s petition to impress a receivership on his assets had been dismissed by the trial court in which divorce proceedings between Saekett and his wife were pending; that he was “ready, eager and willing to proceed to . . . consummate all details of our previously settled sale and purchase”; and that the decision of the trial court dismissing his wife’s petition for receivership “will clear way shortly for full financing any unpaid balance.” Accordingly, Saekett, in this telegram, urged Spindler to have his attorney contact Sackett’s attorney “regarding any unfinished details.” In response to this telegram Spindler’s attorney, on October 5, wrote a letter to Sackett’s attorney stating that as a result of Sackett’s delay in performing the contract and his unwillingness to consummate the agreement, “there will be no sale and purchase of the stock. ...” Following this letter Sackett’s attorney, on October 6, telephoned Spindler’s attorney and offered to pay the balance due under the contract over a period of time through a “liquidating trust.” This proposal was rejected by Spindler’s attorney, who, however, informed Sackett’s attorney at that time that Spindler was still willing to consummate the sale of the stock provided Saekett would pay the balance in cash or its equivalent. No tender or offer of cash or its *227equivalent was made and Sackett thereafter failed to communicate with Spindler until shortly before the commencement of this action.

Beginning during the period scheduled for Sackett’s performance of the contract Spindler found it increasingly difficult to operate the paper at a profit, particularly due to the lack of adequate working capital. In an attempt to remedy this situation Spindler obtained a loan of approximately $4,000 by mortgaging various items of personal property owned by him. In addition, in November, Spindler sold half of his stock in S & S Newspapers for $10,000. Thereafter, in December, in an effort to minimize the cost of operating the newspaper, Spindler converted the paper from a daily to a weekly. Finally, in July 1962 Spindler repurchased for $10,000 the stock which he had sold the previous November and sold the full 6,316 shares for $22,000, which sale netted Spindler $20,680 after payment of brokerage commission.

Breach, of Contract

Sackett contends that the evidence reveals no “actionable breach” on his part. The basis of his argument is that despite his failure to tender over half of the purchase price for the stock of S & S Newspapers, his duty to consummate the contract was discharged by Spindler’s conduct in two respects, namely, Spindler’s “rescission” of the purchase agreement as a result of his reclamation of the stock certificates from Sackett’s attorney on September 1 and Spindler’s “repudiation” of the contract on October 5.

To begin with, the undisputed evidence shows that of the $85,000 due from Sackett to Spindler under the purchase agreement the total amount which the former paid to the latter up to the time of trial was $29,744.26. Moreover, the purchase agreement reveals that Sackett’s promise to pay Spindler $85,000 was an unconditional one once the respective dates on which the payments were due had arrived. Accordingly, since the trial court found that it was not impossible for Sackett to perform the subject contract either by virtue of his illness and hospitalization or his pending divorce litigation, it is clear that his failure to tender the balance due under the contract constituted a breach of the agreement, a breach being defined as an unjustified or unexcused failure to perform all or any part of what is promised in a contract. (Rest., Contracts, §§ 312, 314, pp. 462, 465.) The question remains, therefore, as to whether Sackett’s duty to consummate the contract *228or to respond to Spindler in damages for the former’s failure to perform the subject contract was in any way discharged by Spindler’s conduct.

With regard first to Spindler’s reclaiming of the stock which he had previously delivered to Sackett’s attorney to hold in escrow until Sackett paid the balance due under the contract, Sackett argues that under the Uniform Stock Transfer Act (Corp. Code, §§2450 through 2486), which was in effect at the time of the transactions involved in this action,2 Spindler’s delivery of the endorsed shares of stock to Sackett’s attorney served to transfer title to these shares (Corp. Code, § 2466), and that by subsequently reclaiming the shares of stock Spindler effected a rescission of the purchase agreement and thus barred himself from being able to recover damages for Sackett’s breach of the contract.

In response to this contention we note initially that although former Corporations Code, section 2466 provided that ‘ ‘ Title to a certificate and to the shares represented thereby can be transferred ... (a) By delivery of the certificate endorsed either in blank or to a specified person by the person appearing by the certificate to be the owner of the shares represented thereby,” it is apparent that delivery of such endorsed stock certificates into escrow does not constitute a transfer of title to the stock within the purview of this section. Moreover, even if such delivery did constitute a transfer of title to the stock, a subsequent reclaiming of the stock certificates would not work a rescission of the contract pursuant to which the stock certificates were delivered into escrow. The procedure by which a unilateral rescission of a contract is effected is set forth in Civil Code, section 1691, as follows: ”... to effect a rescission a party to the contract must promptly . . . (a) Give notice of rescission to the party as to whom he rescinds; and (b) Restore to the other party everything of value which he has received from him under the contract or offer to restore the same upon condition that the other party do likewise. ...” Spindler did neither of these acts in connection with his withdrawal of the stock certificates from escrow on September 1. Rather, even after that date he continued to affirm the contract and to urge Sackett to perform it. Thus, it is clear that Spindler neither intended to rescind the contract as of September 1 nor took any action *229which could effect such a rescission.3 Secondly, with regard to Sackett’s claim that Spindler "repudiated” the contract on October 5, it is clear that the letter which Spindler’s attorney wrote to Sackett’s attorney on that date informing the latter that as a result of the "many delays” on the part of Sackett "there will be no sale and purchase of the [newspaper] stock” constituted notification to Sackett that Spindler considered his own duty of performance under the contract discharged as a result of Sackett's breach of the contract and that Spindler was thereby terminating the contract and substituting his legal remedies for his contractual rights. Such action was justifiable on Spindler’s part if, but only if, Sackett’s breach could properly be classified as a total, rather than a partial, breach of the contract. (Rest., Contracts, § 313, p. 464; 4 Corbin on Contracts, § 946, p. 809.) If, on the other hand, Sackett’s breach at that time was not total so that Spindler was not entitled to consider himself discharged under the contract, then Spindler’s action would constitute an unlawful repudiation of the contract, which would in turn be a total breach of the contract sufficient to discharge Sackett from any further duty to perform the contract. (6 Corbin on Contracts, § 1253, pp. 7, 13-16.)

Whether a breach of contract is total or partial depends upon its materiality. (Rest., Contracts, § 317, p. 471.) In determining the materiality of a failure to fully perform a promise the following factors are to be considered: (1) The extent to which the injured party will obtain the substantial benefit which he could have reasonably anticipated; (2) the extent to which the injured party may be adequately compensated in damages for lack of complete performance; (3) the extent to which the party failing to perform has already partly performed or made preparations for performance; (4) the greater or less hardship on the party failing to perform in terminating the contract; (5) the wilful, negligent, or innocent behavior of the party failing to perform; and (6) the greater or less uncertainty that the party failing to perform will perform the remainder of the contract. (Rest., Contracts, § 275, pp. 402-403.) In the instant ease, although *230Sackett had paid part of the purchase price for the newspaper stock and although his delay in paying the balance due under the contract could probably be compensated for in damages, we are of the opinion that Spindler was justified in terminating the contract on October 5 on the basis that despite Sackett’s “offers” to perform and his assurances to Spindler that he would perform, it was extremely uncertain as to whether in fact Sackett intended to complete the contract. In addition, in light of Spindler’s numerous requests of Sackett for the balance due under the contract, the latter’s failure to perform could certainly not be characterized as innocent; rather it could be but ascribed to gross negligence or wilful conduct on his part.

The facts in the instant case are similar to those in Coughlin v. Blair, 41 Cal.2d 587 [262 P.2d 305], There the plaintiffs purchased a lot from the defendants, who, in the deposit receipt evidencing the sale, agreed to install utilities and to pave the road to the subject lot within one year from the date of the agreement. On May 30, 1949, the date that performance was due under the contract, the utilities had not been installed nor had the road been paved. During the following year the plaintiffs wrote several letters to the defendants demanding performance. The defendants, however, did not perform their obligations nor did they repudiate the contract. Ultimately, on May 24, 1950, the work still not having been done, the plaintiffs brought an action for general damages based on the difference in value of the property with and without the performance promised in the contract and for special damages. In affirming the judgment of the trial court insofar as it awarded the plaintiffs general damages, the Supreme Court considered whether, in view of the defendants’ assertion that they intended to perform their obligations under the contract in the future, the trial court’s award of damages to the plaintiffs allowed them a double recovery, that is, both the improvements and damages for failure to secure the improvements. In this context the Supreme Court pointed out that if the defendants ’ breach was total, the plaintiffs could recover all their damages, past and prospective, in one action and that a judgment for the plaintiffs in such an action would absolve the defendants from any duty to perform the contract. The Supreme Court then proceeded to consider whether the plaintiffs were entitled to treat the defendants’ breach as total as of the date of the commencement of the action and concluded that “Although defendants had not expressly repudiated the con*231tract, their conduct clearly justified plaintiffs’ belief that performance was either unlikely or would be forthcoming only when it suited defendants’ convenience.” Under these circumstances it was held that the plaintiffs were not required to endure that uncertainty or to await the defendants’ convenience but were justified in treating the defendants’ nonperformance as a total breach of the contract. (Pp. 599-600 ; see also Gold Min. & Water Co. v. Swinerton, 23 Cal.2d 19, 29-30 [142 P.2d 22]; Walker v. Harbor Business Blocks Co., 181 Cal. 773,780-781 [186 P. 356].)

Similarly, in the instant case although Sackett at no time repudiated the contract and although he frequently expressed willingness to perform, the evidence was such as to warrant the inference that he did not intend to perform the subject contract. Certainly, the state of the record was such as to justify the conclusion either that it was unlikely that Sackett would tender the balance due or that he would do so at his own convenience. Spindler was not required to endure the uncertainty or to await Sackett’s convenience and was therefore justified in treating the latter’s nonperformance as a total breach of the contract. Accordingly, we conclude that the letter which Spindler’s attorney wrote to Sackett’s attorney on October 5 did not constitute an unlawful repudiation of the contract on Spindler’s part, was therefore not a breach of the contract by him, and thus did not discharge Sackett’s duty to perform the contract or, alternatively, to respond to Spindler in damages.

In any event, even if Spindler was not justified in treating Sackett’s breach as total as of October 5, the latter’s contention that his duty to perform was discharged by Spindler ’s repudiation of the contract as of that date is untenable. Since Spindler was not obligated to perform his promise at that time due to Sackett’s failure to tender the balance due under the contract, Spindler’s repudiation was, at best, anticipatory in nature. Its effect was nullified by Sackett’s disregard of it and his treating the contract as still in force as evidenced by his attempt, through his attorney, to arrange an alternative method of financing the balance due under the agreement. (See Cook v. Nordstrand, 83 Cal.App.2d 188, 195 [188 P.2d 282]; Rest., Contracts, § 319, p. 481.) Moreover, Spindler’s repudiation was itself retracted by his attorney who, on Spindler’s behalf, told Sackett’s attorney in the same conversation at which the latter suggested an alternative method of financing that Spindler was still willing to eonsum*232mate the sale provided Sackett would pay the balance due in cash or its equivalent. Such a retraction constitutes a nullification of the original effectiveness of the repudiation. (Rest., Contracts, § 319, p. 481.)

Measure of Damages

As revealed in the findings of fact in the instant case, the $34,575.74 award of damages to Spindler was calculated by subtracting from the $85,000 contract price all sums of money received by him from Sackett ($29,744.26) and Spindler’s net proceeds from his subsequent sale of the stock in July 1962 ($20,680). Sackett contends that the trial court erred in measuring damages by the difference between the contract price for the stock and the price at which Spindler ultimately resold the stock to a third party and that the proper measure of damages in the instant case should instead have been the difference between the price which Sackett agreed to pay for the stock and its value at the date of the breach. In addition, Sackett argues that even assuming the trial court used the correct measure of damages it erred in its computation of damages under this measure. In this regard he contends that since, under his contract with Spindler, he not only agreed to pay Spindler $85,000 but also agreed to assume the liabilities of the newspaper, which at the time of the agreement amounted to $201,849.33, and since under Spindler’s sale of the stock in 1962 the buyer was also to assume the newspaper’s liabilities, which at that time were approximately $219,844.63, the increase in liabilities during this interval, i.e., $17,995.30, constituted “gross income” to Spindler and “should have been deducted from the judgment as money which had been received by the seller.” We concern ourselves initially with the question of what measure of damages was appropriate in the instant ease.

Sackett concedes that under the holding of Porter v. Gibson (1944) 25 Cal.2d 506, 511-514 [154 P.2d 703], the provisions of the Uniform Sales Act (Civ. Code, §§ 1721-1800),4 which was in effect at the time of the subject transaction, are not applicable to a sale of corporate stock.5 (See also Franck v. J. J. Sugarman-Rudolph Co. (1952) 40 Cal.2d 81, 87-88 [251 P.2d 949].) Accordingly, section 1784 of the Uniform Sales Act providing that the seller’s measure of damages for the buyer’s breach of a contract to purchase goods is the *233difference between the contract price and the market price at the time of the breach is not applicable in the instant case. While under the holding of the Porter case the provisions of the Uniform Sales Act are not applicable to a sale of corporate stock, that case, in holding that upon the vendee’s breach of a contract to purchase stock when the title to it had passed the vendor may retain the stock for the vendee and sue for the purchase price, applied the law applicable to sales of personal property as that law is articulated in Cuthill v. Peabody (1912) 19 Cal.App. 304 [125 P. 926]. Moreover, since the principles of the Cuthill case, as applied by Porter, were approved in Franck, we deem them applicable here.

The Cuthill case, decided prior to the adoption of the Uniform Sales Act, was an action by the vendor of shares of stock against the vendee to recover the purchase price of the stock, which the vendee had contracted to purchase. In considering whether such a remedy was available to the vendee, the appellate court applied to sales of corporate stock the provisions of the Civil Code and rules of law in cases dealing with personal property, as those rules existed before the adoption of the Sales Act. Based upon those principles, the court in Guthill concluded that since the title to the stock had passed, the vendor could sue for the purchase price. However, in its opinion, the court articulated the rule that where title to corporate stock has not passed, the vendor, upon the refusal of the vendee to accept the stock and pay the agreed price therefor, cannot sue for the purchase price but is compelled to recoup his loss, if any, solely by an action for damages founded upon a breach of the vendee’s contract to accept and pay for the property. (P. 308.) In this regard, Guthill noted that the applicable remedy, under the general rule, is that ‘1 The vendor may treat and keep the property as his own, and recover from the vendee the difference between the contract price and the market price at the time and place of delivery [citations].” (P. 308.)

Cuthill, suggests, by a mere citation of section 3311 which was then in force, and without any discussion of the applicability of that section, that the applicable remedy, upon the vendee’s breach of a contract for the purchase of property to which title has not passed, is that provided for in that statute. Section 3311 provided, essentially, that the measure of damages for the buyer’s breach of a contract to accept and pay for personal property where title was not vested in the purchaser and the property was not resold in the manner *234provided by section 30496 is the difference between the price which the purchaser agreed to pay and the value of the property to the seller. That section was qualified by section 3353, which provided that the value of the property to a seller is deemed to be the price obtainable therefor in the market nearest to the place at which the property should have been accepted by the buyer and at such time after the breach of the contract as would have sufficed, with reasonable diligence, for the seller to effect a resale.7 (See Willson v. Gregory, 2 Cal.App. 312, 314 [84 P. 356]; Meyer v. McAllister, 24 Cal. App. 16, 17 [140 P. 42]; Lillie v. Weyl-Zucherman & Co., 45 Cal.App. 607, 610 [188 P. 619]; California P. G. Assn. v. Herspring, 60 Cal.App. 503, 511-512 [213 P. 518]; Hill v. McKay, 94 Cal. 5, 17-18 [29 P. 406] ; Hewes v. Germain Fruit Co., 106 Cal. 441, 446-447 [39 P. 853] ; and see Royer v. Carter (1951) 37 Cal.2d 544, 549 [233 P.2d 539].)

In 1931 when the Legislature adopted the Uniform Sales Act, it repealed section 3311. Section 3353, however, was retained and still remains in the Civil Code. In Boyer, which was an action for breach of a contract to purchase realty, section 3353 was held to be inapplicable to real property on the basis that its language suggests that it is limited to sales of personal property. Accordingly, the Supreme Court concluded that since section 3353 has no application to the sales of real property, the applicable rule in cases involving sales of real property, in the light of the provisions of section 3307,8 was the general rule which required that damages be computed as of the date of the breach of the agreement to purchase the property. (Pp. 549-550.) In Honey v. Henry’s Franchise Leasing Corp. (1966) 64 Cal.2d 801 [52 Cal.Rptr. 18, 415 P.2d 833], a case involving a contract to purchase real and personal property, the Supreme Court, although it sent the case back to the lower court for retrial on the issue of damages because the vendor repossessed some of the property before trial and it was ‘“impossible to determine from the *235record whether the value of all the property at the time of the trial was equal to its value at the time of the breach plus any consequential damages that may have been incurred” (p. 805), reiterated the rule of the Boyer case and the interpretation which it had, in that case, placed on section 3307. We note, moreover, that while Honey involved both real and personal property, and while its holding turned essentially on the interpretation of section 3307, which applies only to real property, the Supreme Court in that case made no distinction between real and personal property.

The Royer case, moreover, specifically noted that section 3353 was invoked by the courts before the adoption of the Uniform Sales Act to define the term “value to the seller” as used in former section 3311. Although section 3353 is still extant and has now been specifically restricted to cases involving personal property, it is doubtful that it now has any efficacy in view of the repeal of section 3311, which section it was intended to qualify. Since section 3353 comes into play when the “value of property to a seller” is to be utilized in estimating damages, it would have no applicability to personalty which came within the purview of the Uniform Sales Act, the measure of damages for the buyer’s breach of a contract to purchase goods under section 1784 being the difference between the contract price and the market price at the time of the breach.9 We conclude, therefore, that insofar as corporate stock is concerned we are, by virtue of the repeal of section 3311, relegated to the general rule articulated in Cuthill that where title to the stock has not passed, the measure of damages for breach of a contract to accept and pay for the stock is the difference between the contract price and the market price at the time and place of delivery.

It is the general rule, both under the Uniform Sales Act and apart from it, that where the title to goods has not passed to the buyer and the seller has the property in his possession or under his control, the measure of damages upon the buyer’s refusal to accept and pay for goods for which there is an available market is, in the absence of special circumstances, the difference between the contract price and the market or current price or value at the time and the place where the goods ought to have been delivered and accepted, or, if no time is fixed for acceptance, then at the time of the refusal to accept. (78 C.J.S. Sales, § 478, p. 137; see Southern *236Pac. Mill Co. v. Billiwhack etc. Farm (1942) 50 Cal.App.2d 79, 87 [122 P.2d 650].) As used in this measure, the words “market price” and “market value” mean the same thing, that is, the price or value of the article as established or shown by sales in the way of ordinary business; the price at which goods are freely offered in the market to all the world. (Southern Pac. Mill Co. v. Billiwhack etc. Farm, supra, p. 88; Kings County Packing Co. v. Sunland Sales etc. Assn. (1929) 100 Cal.App. 126, 133 [279 P. 1036]; 78 C.J.S., supra, p. 138.)

The above-stated measure of damages, however, does not ordinarily apply when there is no market available at the time and place of performance. In such eases resort may be had to the market value of the goods at the nearest available market; and in the absence of an available market, it has been held that the measure of damages may be the difference between the contract price and the value of the goods as best as can be ascertained, or the difference between the contract price and the best offer that can be obtained for the goods, or the difference between the contract price and the price obtained on a resale, or the actual damages naturally and directly resulting from the buyer’s breach. (78 C.J.S., supra, § 478(c) and cases cited; and see Los Angeles Coin-O-Matic Laundries v. Harow, 195 Cal.App.2d 324, 331-335 [15 Cal.Rptr. 693]; and see subd. (2) of former § 1784 and Com. Code, § 2708.) Moreover, even where there is an available market, ‘ ‘ The general rule that the measure of damages is the difference between the contract price and the market value is not a hard-and-fast rule, but may be varied if circumstances require it; and it will not be followed where a better method of measuring loss or damages is available under the circumstances.” (78 C.J.S., supra, p. 138; see subd. (3) of former § 1784; Com. Code, § 2708; and see Los Angeles Coin-O-Matic Laundries v. Harow, supra.)

It is apparent from the foregoing principles that the measure of damages applied by the trial court in the instant case, namely, the difference between the contract price and the net amount of $20,680 received by Spindler from the resale in July 1962, was proper under the circumstances of this case since the record contains evidence from which the trial court could properly conclude that there was no available market for the stock at the time of Sackett’s breach. We refer to the testimony of Joseph Snyder, a newspaper broker, to the effect that because the prospective sale of the newspaper by Spindler to Sackett had been publicized in the local newspaper, the former would have great difficulty making a resale *237of the newspaper after the latter’s failure to consummate the purchase agrément, and that Spindler was in fact extremely fortunate to sell his stock in July 1962. In view of this evidence which tends to show the unavailability of a market for the stock at the time of the breach, we conclude that the trial court was entitled to use the resale price in determining Spindler’s damages. Finally, we need not consider whether the trial court, in using the resale price to measure Spindler’s damages, should have valued the stock after the breach at $20,000 based upon the sale which Spindler made of one-half of the stock for $10,000 in November 1961. The fact that the trial court used the ultimate net sale price of $20,680 to determine the value of the stock served only to benefit Sackett since a comparison of these two figures show that the value of the stock had increased by the time of the second sale.

Having concluded that the trial court applied the correct measure of damages in the instant case, we consider Sackett’s argument that in computing damages under this measure the trial court should have taken into consideration the fact that the liabilities of the newspaper increased some $17,995.30 during the one-year period between the time he agreed to purchase Spindler’s stock and the sale of the stock which the latter ultimately effected. This contention is without merit for the reason that both agreements of sale involved an exchange of the stock of S & S Newspapers for a fixed amount of money, in the one ease $85,000 and in the other $22,000. The newspaper’s liabilities at each of these times, or more properly the relationship of its liabilities to its assets, was obviously a primary factor in determining the amount which each buyer was willing to pay for the stock and was thus reflected in the contract price of the stock at each date. To this extent the increase in the newspaper’s liabilities was necessarily and properly considered by the trial court in awarding damages to Spindler. Any separate or additional consideration by the trial court of the increase in liabilities would have been improper.

Evidence As to the Value of the Stock at the Date of Breach

Based upon his contention that the proper measure of damages in the instant case should have been the difference between the contract price for the stock and the value of the stock at the date of breach, Sackett contends that the trial court erred in excluding evidence concerning the value of the stock as of the date of breach. The evidence which Sackett *238claims the court erroneously excluded was not directed to the value of the stock as of the date of the breach, but, rather, to the value of the business as of October 5. This evidence was sought to be elicited from Spindler on cross-examination. The record discloses that Spindler, when queried as to the value of the business as of October 5, testified that he did not know its value as of that date, but that it was less than the $85,000 which Sackett had agreed to pay. The objection which the trial court sustained was to an argumentative question by Sackett’s counsel as to whether Spindler agreed with Snyder ’s testimony that the value of a weekly newspaper was the annual gross of the business. The objection was sustained on the ground that the question assumed a fact not in evidence on the basis that Snyder had not so testified. Although the colloquy which followed between court and counsel elicited a statement from the court that it deemed the value of the business two or three weeks after July 8, the date of the sale, as immaterial, the record is unclear as to whether the trial court understood that Sackett’s counsel was attempting to show by his argumentative question the value of the stock as of the date of the breach. While the subject was not pursued after the colloquy, we cannot say from a perusal of the record that the trial court foreclosed Sackett’s counsel from making the showing he now asserts he was precluded from making.

Mitigation of Damages

The trial court specifically found that Spindler “spent all reasonable efforts in minimizing damages to plaintiff . . .” and that “The diminution in value of the ‘S & S Newspapers’ ’ business after September 9, 1961 and the consequent diminution in value of the corporate stock in ‘S & S Newspapers’ after September 9, 1961 was directly caused by the conduct of plaintiff ... in breaching the aforesaid contract of July 8, 1961 and plaintiff [’s] . . . failure to pay to defendant . . . the entire purchase price on or before October 5, 1961.” Sackett contends that these findings are not supported by the evidence.

! It is well established in California that a party injured by a breach of contract is required to do everything reasonably possible to minimize his own loss and thus reduce the damages for which the other party has become liable. (Valencia v. Shell Oil Co., 23 Cal.2d 840, 844 [147 P.2d 558]; Johnson v. Comptoir etc. D’Exportation, 135 Cal.App.2d 683, 689 [288 P.2d 151]; Hunter v. Croysdill, 169 Cal.App.2d 307, 318 [337 P.2d 174].) From this rule it follows that a person *239who has been injured by a breach of contract cannot recover damages for detriment which he could have avoided by reasonable effort and without undue expense. (Hunter v. Croysdill, supra; Murphy v. Kelly, 137 Cal.App.2d 21, 31 [289 P.2d 565]; Valencia v. Shell Oil Co., supra.) The question of whether the injured party has acted reasonably in mitigating damages is one of fact. (Jegen v. Berger, 77 Cal.App.2d 1, 11 [174 P.2d 489].) Accordingly, where, as in the instant case, the trial court has made findings of fact to the effect that the injured party has acted reasonably in minimizing his damages, this finding must be upheld on appeal if the record contains any substantial evidence in support of such finding.

In the instant case it is clear that the record contains ample evidence tending to show that Spindler acted reasonably in minimizing damages. Firstly, in order to improve the financial condition of the newspaper he made several efforts to raise working capital for the business. This he did by personally borrowing money for additional capital and by selling one-half of his stock. In addition, he cut costs by changing the newspaper from a daily to a weekly paper. Sackett argues that after Spindler had determined that Sackett had breached the contract, Spindler did not list the newspaper for sale with a broker nor did he take any other steps to sell the newspaper. However, according to Snyder’s testimony, such action on the part of Spindler would have been futile since it would be almost impossible for him to sell the newspaper after the publicized sale to Sackett had fallen through. In addition, since the record reveals that, the financial condition of the newspaper immediately after Sackett’s breach was worse than its financial condition approximately one year later, it is apparent that Spindler’s damages would have been greater if he had been able to sell the stock at an earlier date. Finally, Sackett contends that Spindler was required to accept Sackett’s so-called “offer” of October 4 in order to minimize damages. However, Sackett’s telegram of October 4 contained no tender of performance, but only an expression of willingness to proceed to consummate the sale as soon as the release of his assets from threatened receivership in his divorce action would permit “full financing” of the unpaid balance.

The Propriety of the Interest Award

In addition to awarding Spindler damages in the amount of $34,575.74, the trial court awarded him interest on that sum *240at 6 percent from September 29 to the date of entry of judgment. Sackett contends that this award of interest was error. With this contention we agree. Section 3287 provides for the inclusion of interest in an award of damages as follows: “Every person who is entitled to recover damages certain, or capable of being made certain by calculation, and the right to recover which is vested in him upon a particular day, is entitled also to recover interest thereon from that day, except during such time as the debtor is prevented by law, or by the act of the creditor from paying the debt. ...” (See Axell v. Axell, 114 Cal.App.2d 248, 255-256 [250 P.2d 182].) In Maurice L. Bein, Inc. v. Housing Authority, 157 Cal. App.2d 670, 686 [321 P.2d 753], the applicable principle is stated as follows: “As a general rule interest in the form of damages is not allowed prior to rendition of judgment on an unliquidated claim or on the amount of a demand which cannot be ascertained either from the face of the contract or by reference to a well-established market value.” (See also Tomlinson v. Wander Seed & Bulb Co., 177 Cal.App.2d 462, 476 [2 Cal.Rptr. 310]; see also Axell v. Axell, supra, 256; Lineman v. Schmid, 32 Cal.2d 204, 212 [195 P.2d 408, 4 A.L.R.2d 1380].) These principles preclude Spindler ’s recovery of interest in the instant case for two reasons. In the first place, since Saekett did not expressly repudiate his agreement with Spindler, the exact date of breach for the purpose of calculating interest is not certain. Secondly, since there was no available market at the time of the breach, the court was required to determine the market price based upon other factors. It follows, therefore, that since Spindler’s damages could not be made certain without this determination of market value by the court, interest was not properly awarded to him.

The judgment is modified by deleting therefrom the award of interest from September 29,1961 to the date of the entry of judgment. As so modified, the judgment is affirmed. Respondent Spindler to recover costs.

Sims, J., and Bray, J.,* concurred.

Appellant’s petition for a hearing by the Supreme Court was denied March 29, 1967. Sullivan, J., did not participate therein.